Germany: Act on Energy Efficiency
Covers energy efficiency renewable energy and disclosure for data centers comes closer
May 05, 2023
Germany: Act on Energy EfficiencyCovers energy efficiency renewable energy and disclosure for data centers comes closerMay 05, 2023 The German Government has adopted the bill of the Federal Ministry for the Economy for an “Act to Enhance Energy Efficiency and to Amend the Energy Services Act” (Energieeffizienzgesetz, EnEfG) and will introduce it in Parliament. This Act will seriously affect operators and users of data centers: Requirements for efficiencyPower usage effectiveness and energy reuseData centers which start operations before 1 January 2026 must have:
Data centers which are commissioned 1 January 2026 or later must have:
These requirements must be fulfilled at the latest two years after start of operations and on a lasting basis thereafter. When calculating the Power Usage Effectiveness, electric power used for reinforcing the waste heat of the data center will not be taken into account. Minimum air cooling temperatureData centers starting operations on 1 January 2024 or later may not implement air cooling for information technology with an entry temperature lower than 27°C, unless such lower temperature can be achieved without a cooling system. Data centers starting operations before 1 January 2024 may implement a minimum temperature of 24°C, which minimum temperature will rise to 27°C on 1 January 2028. Definition of “data center”“Data center” shall be defined to comprise structures for housing information technology and telecommunication network equipment for storing, processing, and transporting data, and equipment and infrastructure for securing the service with a non-redundant nominal power connection capacity of 200 kW or more. Obligation to use unsubsidized renewable powerData centers will have to source electric power from renewable energy plants which power does not benefit from support pursuant to the Renewable Energies Act (Erneuerbare-Energien-Gesetz), the Combined Heat and Power (CHP) Production Act (Kraft-Wärme-Kopplungsgesetz) or other aid in the meaning of the Renewable Energies Directive of 11 December 2018 (“unsubsidized power”),
Use of waste heatAll businesses, including data centers, with an annual average end energy consumption of 2.5 GWh or more will be obliged to avoid and reduce waste heat unless technically inevitable, to re-use waste heat in their own premises and to provide it to third parties, and to implement measures and installations. Upon request, such businesses will have to inform heat suppliers, other possible buyers of heat about the quantities and availability of waste heat from their operations, possibilities to control temperature and feed-in, temperature level and prices. Every year on 31 March, they will have to submit that data to the Federal Office for Energy Efficiency (Bundesstelle für Energieeffizienz, which is part of the Bundesamt für Wirtschaft und Ausfuhrkontrolle, Bafa). The Energy Reuse Factor (see above the “Requirements for Energy Efficiency”) will not apply if an agreement between the data center operator and a municipality or heat network operator is in place by which the municipality or network operator states its intention to build or allow heat networks by which the requirements on energy reuse will be fulfilled within 10 years. That agreement must provide, among others, for an investment plan. The data center operator will also be relieved from the Energy Reuse Factor if:
The Government, according to the explanations to the draft, wishes that sites for data centers nearby heat networks be preferred. Energy and environmental management systems for data centersData center operators will have to implement an energy or environmental management system until 1 July 2025 at the latest. If the data center has a nominal connection capacity of one MW or more, the energy or environmental management system must be certified or validated according to Regulation (EC) 1221/2009 beginning 1 January 2025. The same will apply mutatis mutandis to operators of information technology with a capacity of 500kW or more, beginning 1 January 2025. Lower thresholds, 200kW, are pertinent for data centers and information technology owned by state entities. “Operators of information technology” will be individuals or legal entities which operate information technology within a data center of non-redundant nominal power of 50 kW or more, but which are not operators of that very data center. Disclosure obligations for operators of data centers and of information technologyData center operators and operators of information technology are held to submit specific information on the data center, its use of energy and production of waste heat, some of which will be published, other, more sensitive items of information, stored for calculations and information to public authorities. In addition, to the extent operators of data centers provide services to customers, they will be obliged to inform the customers about their respective energy consumption (starting 1 January 2024) and, if they practice co-location, to provide incentives and support customers in saving energy and using information technology more efficiently, beginning 1 January 2024. OutlookThe bill has now been adopted by the Government as a whole and will soon be debated and voted in the Council of the States (Bundesrat) and in the Federal Parliament (Bundestag). It is likely that Parliament, where the parties supporting the Government have a majority, adopts the bill at least in its key features and makes it law. In comparison to the draft of the Ministry for Economic Affairs and Climate Protection (Bundesministerium für Wirtschaft und Klimaschutz, BMWK), the Government has taken into account some criticism by industry associations like the German Datacenter Association (GDA) and bitkom, the organization of the IT industry. Some deadlines for data center operators have been extended, however, mainly because some time has passed since the BMWK draft. Data center operators, users and suppliers will have to observe the further legislative procedure carefully and to modify plans and renegotiate agreements, and also reorganize power purchase arrangements with users. Latest Insights
Latest News
Latest Events
legal updates November 17, 2026 Mandatory human rights due diligence is coming to the UK legal updates November 17, 2026 COP31: Science, industry and technology – from pledges to investment pipeli... legal updates November 16, 2026 COP31: Finance, trade and the challenge of turning climate ambition into in... legal updates November 16, 2026 COP31: Children, Youth, Education and Skills Day deal alerts November 06, 2026 Eversheds Sutherland advises Mercedes-Benz on European fast-charging partne... firm news November 05, 2026 Eversheds Sutherland hires partner Peter Cheng to lead Hong Kong ECM practi... firm news October 27, 2026 Eversheds Sutherland (International) announces senior leadership appointmen... firm news October 26, 2026 Eversheds Sutherland deepens fintech and regulatory bench with double partn... hybrid Europe Action Week 2026 Europe Action Week returns this November with a dynamic mix of events designed to help you navigate what’s next. virtual Belgian employment law training November 17, 2026 2.00pm - 5.00pm (GMT) Virtual in-person Industrial relations masterclass November 18, 2026 9.30am - 4.30pm (GMT) London, United Kingdom virtual Immigration UK Business – sponsor licencing course November 24, 2026 9.30am - 11.30am (GMT) Virtual |