BGH ruling allows building cost contributions for battery storage
July 15, 2025
BGH ruling allows building cost contributions for battery storageJuly 15, 2025 Why should I read this?The German Federal Court of Justice (Bundesgerichtshof - “BGH”) has issued a landmark decision this 15 July 2025 (Case EnVR 1/24) confirming that power network operators may charge building cost contributions (Baukostenzuschüsse - “BKZ”) for the grid connection of a battery energy storage system (“BESS”) as for any off-taker. Hopes in the industry for reduced BKZ and more favourable treatment of BESS have been spoiled. Implications for the economics of BESS projects in Germany may be important. What do I need to know?The BGH reverses the ruling of the Düsseldorf Court of Appeals (Oberlandesgericht) of 20 December 20231 and reinstates the original decision of the Federal Network Agency (Bundesnetzagentur - “BNetzA”)2. As a result, network operators are entitled to levy a BKZ for BESS based on the demand price for network access in the relevant voltage level in accordance with the relevant BNetzA position papers, even if these systems do not consume electricity in the traditional sense but instead temporarily store and re-inject it into the grid. The opinion of the BGH and its reasoning are not yet available. The press release3 of the BGH outlines the following considerations:
What does this mean for stakeholders?Network operators may continue applying BKZ to BESS projects, subject to transparency and non-discrimination, but are not obliged to. According to the BGH, network operators have a margin of discretion to apply reduced BKZ for storage facilities. BESS developers and operators must as a general rule still factor in BKZ as a non-negotiable cost component of network connections, payable upfront as a prerequisite for network connection and depending on the network access fees charged by the specific network operator. In the case at hand, for a high-voltage connection of 1.724 MW, the BKZ could amount to EUR 189,640 (Mitnetz Strom GmbH in Eastern Germany) or EUR 284,822 (SWM Infrastruktur GmbH & Co. KG in the City of Munich). For very large BESS projects with capacities of more than 100 MW, these will be two-digit million amounts. What should I do next?Project developers and investors should monitor legislative and regulatory developments:
Network operators in several parts of Germany report long “queues” for feed-in capacity for BESS projects. It must be assessed for the project at hand whether to apply for connection capacity lower than the peak capacity of the system and/or to combine BESS with PV, wind or load projects, such as data centres.
Latest Insights
Latest News
Latest Events
legal updates November 25, 2026 Sanctions updates in Europe: November 2026 legal updates November 25, 2026 Commercially Connected - November 2026 legal updates November 23, 2026 COP31: Talks conclude without an overarching agreement legal updates November 23, 2026 Offshore Wind - From record results to delivery client news November 19, 2026 Eversheds Sutherland advises EDF on landmark UK energy retail acquisition deal alerts November 06, 2026 Eversheds Sutherland advises Mercedes-Benz on European fast-charging partne... firm news November 05, 2026 Eversheds Sutherland hires partner Peter Cheng to lead Hong Kong ECM practi... firm news October 27, 2026 Eversheds Sutherland (International) announces senior leadership appointmen... hybrid Europe Action Week 2026 Europe Action Week returns this November with a dynamic mix of events designed to help you navigate what’s next. virtual UK employment law training December 01, 2026 1pm - 4pm (GMT) Virtual virtual Strategic Reflections on COP31 December 02, 2026 10am GMT | 11am CET Virtual, virtual Energy Transition Series - Successfully Tendering Energy Projects In Saudi ... December 08, 2026 7:00 ET |12:00 GMT | 13:00 CET | 16:00 GST |